The Coast Guard says its North Charleston base is in the middle of a project worth more than $640 million. New piers, engineering shops, barracks and a clinic run to 2030.
Overview
Coast Guard Base Charleston in North Charleston is being rebuilt in a capital project worth more than $640 million, the Coast Guard said. The plan includes new piers, engineering shops, barracks and a medical and dental clinic. The largest single contract, worth $230 million, runs to October 2030.
The Coast Guard gave the total in photos of the work it published Nov. 8 on DVIDS, the Defense Department’s media service. The captions say the work will make Base Charleston “a premier East Coast operational base.”
What is being built
The Coast Guard’s captions list these parts of the project:
- new piers, named Pier November and Pier Mike
- new engineering facilities
- barracks
- a medical and dental clinic, shown in an artist’s rendering
- a new multipurpose building, which was going up in September
The $230 million contract is the newest large piece. The Coast Guard announced it in a July 10 release. The release called it “the latest phase of a comprehensive, multi-year infrastructure expansion plan at the base.”
The five biggest contracts
Federal spending records show five construction contracts at the base worth more than $60 million each. Together they come to about $648.7 million. The figures below are each contract’s current value in the USASpending.gov record, which can rise when work is added.
| Project | Contractor | Value | Start | Scheduled end |
|---|---|---|---|---|
| Operational support facilities | Brasfield & Gorrie | $230 million | June 16, 2026 | Oct. 15, 2030 |
| Pier Papa rebuild | Whiting-Turner | $132.5 million | July 25, 2022 | Nov. 21, 2026 |
| Pier Mike rebuild | Whiting-Turner | $116.7 million | March 6, 2026 | April 17, 2030 |
| Utilities, roads and clinic | Brasfield & Gorrie | $102.3 million | April 20, 2026 | July 10, 2029 |
| Sector Charleston administration building | RQ-AECOM 2 JV | $67.2 million | July 10, 2023 | April 23, 2027 |
How it started
In September 2025, the Coast Guard said Base Charleston was the first place it spent money from the One Big Beautiful Bill Act. That release said a contract change signed Aug. 25, 2025, paid Whiting-Turner to remove up to 100 submerged concrete piles under the old Pier November.
What it means for you
- Work continues for years. The scheduled end dates in the federal record run from Nov. 21, 2026, for the Pier Papa contract to Oct. 15, 2030, for the support facilities.
- The three newest contracts were all signed this year. They are Pier Mike in March, the utilities, roads and clinic contract in April and the support facilities in June.
- Neither the Coast Guard nor the city has published how many people will be stationed at the base when the work is done, or how much construction traffic to expect.